What should I check at handover?
That the unit matches the plan and specification, that fittings work, that dues match your cost sheet, and that you hold the occupancy documents, before accepting possession.
Inspect the unit
- Dimensions against the plan; rooms, balconies, doors and windows.
- Flooring, paint, tiles, countertops and ceilings for defects.
- Plumbing: run every tap and flush every toilet; check for leaks.
- Electrical: test every switch and point.
- Lifts, parking slot and its number.
Check the paperwork
- Occupancy certificate for the building.
- Final statement matching the cost sheet: legal and maintenance charges, sinking fund.
- Sale deed registration and khata transfer plan.
- Transfer of the sinking fund to the Owners’ Association. See sinking fund.
Record defects
Write every snag on a list, get it signed by the developer’s representative, and keep photographs. Under RERA, structural defects reported within the defect-liability period are the developer’s responsibility; check the period in your agreement.
Frequently asked questions
Can I refuse possession?
If the unit does not match the agreement you can raise it in writing. Take legal advice.
Talk to SNAP Realty about Assetz Codename Sublime
Ask for the current cost sheet, the latest availability and a site-visit slot. We answer on WhatsApp the same day.
Register Your Interest
Takes 15 seconds. Our team calls back within the day.
Zero spam calls.